Project Work Began August 24, 2023

New Door & Frame
Powder Coat Finish

Doors, New Stored
Powder Coat Finish

Door Frames, New Stored
Powder Coat Frames, Including Inside to Prevent Rust.

Demolition Saw
Saw used to cut old frames from concrete block construction.

3E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

3E Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

3W New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

2E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

2E New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

2W New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

Unit 1 New Door Rough In
Minor Stucco Damage will be repaired and Painted to Match Existing.

Pool New Door Rough In
Window for light in stairway. Lock elevated for child safety. Minor Stucco Damage will be repaired and Painted to Match Existing.

Det Garage New Door Rough In

East Garage New Door Rough In

West Garage New Door Rough In

East Garage Complete

West Garage Complete

Detached Garage Complete

Unit 1 Complete

Unit 2 East Complete

Unit 2 West Complete

Unit 3 East Complete

Unit 3 West Complete

26-Pool.Cpt